Post Christmas progress

Work started on site for both the One Planet House and the Decent Homes house at the beginning of December.  However, the heavy snowfall in December led to significant delays for the windows and other deliveries.  In addition, more asbestos was found in the Kitchen at the One Planet House, we therefore had a further 2 week delay whilst the Health and Safety Executive were informed. The new kitchen has now been installed in the One Planet House and the Decent Homes house.

The bathroom pod is going into the One Planet House tomorrow and the re-wiring is also happening.  The new timber double glazed windows will be going in at both properties this week too.