Chimneys and ventilation

The final work on the house was to seal up the chimney and to install mechanical extract fans into the kitchen.  Unfortunately neither of these small tasks proved simple!  The original plan was to insert a chimney balloon into the chimney to prevent draughts coming into the house.  However, in order to do this a cap needed to be put on the chimney to prevent things falling onto the balloon.  Although we still had the scaffolding up access to the chimney from the roof was impossible due to the position of the solar panels on the roof.  The solution we decided upon was to brick up the chimney and install a “hit and miss vent” to provide ventilation.

The layout of the kitchen was such that there was no room in the wall for the extract fan.  Usually in houses like ours the fan would be placed in the window.  However, breaking the seal on the glass to install a fan would have had a very detrimental impact on the air tightness of the house.  We therefore had to put the extract fan in the ceiling and run pipework to the outside.

Posted in Uncategorized | Comments Off  

External wall insulation

We had wanted to use the pavatherm woodfibre board for the external wall insulation at the back of the house as well as internally.  However, we were unable to find a system (render + insulation +fixing) that was guaranteed.  Unfortunately we therefore decided to use a more tried and tested system using 70mm of PIR (poly isocyuranate) insulation with a coloured render. The external insulation went on without any problems and the rain stayed away until the render had been applied and dried.  We did have to extend the flue for the boiler so that it protruded from the external insulation.  The photo shows the finished render.

Posted in Uncategorized | Comments Off  

Internal solid wall insulation

We are installing pavatherm woodfibre insulation on the internal walls at the front of the One Planet House.  This is a breathable system that will be finished with a lime plaster.  The lime plaster has a 7 day drying time and therefore to minimise disruption to the tenants we are internally insulating one room at a time.

A piece of the pavatherm board ready to be fixed and the interstitial sensor

A representative from Natural Building Technologies came to the property last week to show the contractor how to put up the woodfibre board and plaster it.

We have decided not to insulate all the way up to the joists of the intermediate floor.  When carrying out internal wall insulation, common sense suggests that we need to insulate all surfaces of external walls to ensure that we are minimising thermal bridges.

However, at this point there is also high susceptibility for uncontrolled air changes through the narrowed mortar joints. Research that Parity Projects have done with the EST and a variety of other contributors has shown that if these parts of the house are insulated, the risk of moisture build up is increased.   This risk is increased when using a breathable insulation system because moisture is able to travel freely through the wall.  As can be seen in the photo opposite, we are also putting interstitial sensors in the walls where there is insulation to measure the moisture of the wall over time.

Posted in Uncategorized | Comments Off  

Windows installed at Thornton Road and Peterborough Road

The timber frame windows that we are using for the project were a significant hamper on our progress.

Their manufacture was delayed due to the snow, which meant that they were not delivered in time to go into the bathroom pod during manufacture.  Because the delivery of the bathroom pod could not be postponed (road closures were required in order to crane it into place), it was decided to leave the PVCu windows in the bathroom pod.  Replacing the windows on site with the timber ones would have led to some very high embodied energy windows and potentially a worse seal around the windows.

The saga didn’t end there.  When the windows arrived at site, five of the windows were not the right size and did not match the dimensions that had been sent to the manufacturer.  These have now been re-made and will arrive on site next week.

Posted in Uncategorized | Comments Off  

Solar thermal and solar photovoltaics installed at Thornton Road

A solar thermal panel (sufficient to supply 60-70% of the household’s hot water demand) was installed on the south facing roof along with solar photovoltaic panels to produce electricity.  The output of these two technologies will be closely monitored.  A pyranometer is also being installed on the roof to monitor their output in comparison to the level of daylight.

Posted in Uncategorized | Comments Off  

Work on the Decent Homes house

So far only the the new kitchen has gone into the Decent Homes house.  Last week some of the new windows arrived.  However, 2 of the windows sent by the manufacturer were the wrong size and have been sent back.  The replacement windows will hopefully be arriving next week.  Meanwhile the electricians are hard at work with the rewiring.

Posted in Uncategorized | Comments Off  

The new bathroom pod in-situ

The new bathroom pod in-situ still to be rendered

The new bathroom pod in-situ, which the resident is able to use while the other work goes on.  The bathroom pod will be rendered to match the render that will be put on top of the external wall insulation in a couple of weeks.

Posted in Uncategorized | Comments Off  

The bathroom pod arrives

The new bathroom pod is craned into position

The old bathroom is taken away

Posted in Uncategorized | Comments Off  

Post Christmas progress

Work started on site for both the One Planet House and the Decent Homes house at the beginning of December.  However, the heavy snowfall in December led to significant delays for the windows and other deliveries.  In addition, more asbestos was found in the Kitchen at the One Planet House, we therefore had a further 2 week delay whilst the Health and Safety Executive were informed. The new kitchen has now been installed in the One Planet House and the Decent Homes house.

The bathroom pod is going into the One Planet House tomorrow and the re-wiring is also happening.  The new timber double glazed windows will be going in at both properties this week too.

Posted in Uncategorized | Comments Off  

The project so far…..

Solar water

Solar water heating

Welcome to the One Planet Sutton retrofit project blog site.

Engaging residents

Between bidding for phase 2 of the retrofit project and winning the bid, two of our participating residents unfortunately had to drop out of the project.  Finding another two residents living in a property the same size, age and orientation as the 1st property was a bit of a challenge but we now have 2 more willing participants for the Decent Homes house and the control house.

Behaviour change programme

Part of developing a successful behaviour change programme is to understand what motivates the target audience and the barriers that they face to changing their behaviour.  Face-to-face and anonymous questionnaires were therefore conducted with each of the residents to identify these motivations and barriers.  BioRegional are now using this information to develop the behaviour change programme, which will comprise 4 workshops with the residents.  The first of which is on the 16th November.

Training for the construction professionals

Russell Smith from Parity Projects ran two training sessions with the main contractor for the project, Lakehouse, sub-contractors and the project management team from Sutton Housing Partnership.  The first training session “Techniques for significantly reducing energy consumption in existing buildings” provided an overview of the different methods of retrofitting energy efficiency measures to buildings, including draught-proofing, internal and external solid wall insulation and roof and floor insulation. Attendees to the session were given the opportunity to take an exam at the end of the session.  Once passed the exam gave them a module in a BTEC qualification, this is to try and stimulate the market for trained retrofit professionals.

The second training session: “Air Tightness and Thermal Bridging in Existing Buildings” provided a more detailed workshop on these two factors for those working on-the project site.  These two areas of retro-fit need the most attention paid to them if we are to achieve the carbon savings required.

Box bathroom and external render planning application

The new box bathroom that is being installed on the One Planet house required planning permission, which was applied for.  Initial consultation with the London Borough of Sutton indicated that the external render to the rear of the property did not need planning permission.  However, when we asked for a lawful development certificate, they reconsidered their position and required us to seek planning approval.  This has unfortunately delayed the project by six weeks.  However, planning permission for the external render was received today, allowing the project to start on site very soon.

Posted in News | Comments Off